| Goal II: Improve the deteriorating physical infrastructure of Sugar Hall (circa. 1971).
[Level: Action (1-2 yrs)]
|
|
|
Responsible Party
|
Timeline*
|
Resources Required
|
Measurable Outcomes
|
Monitoring & Reporting Plan
|
Notes
|
|
a. Renovate the large auditorium style classroom #351.
|
Dean |
6 month |
1. Renovation funds
2. Alternate classroom space. |
Completion of project. |
Bi-weekly College Administrative Council meetings |
Completed in February 2005. |
|
b. Install and support permanent state-of-the-art distance learning classroom technology and equipment in Sugar Hall, as well as the College's satellite campuses located in New Orleans and Shreveport.
|
Dean |
36 month |
1. Acquisition of Shreveport and Baton Rouge facilities
2. Funds |
Completion of project. |
Bi-weekly College Administrative Council meetings |
Completed in Monroe Feb. 05
Expected date of completion for Shreveport: Nov. 06
Expected date of completion for Baton Rouge: Summer 07 |
| c. Update classroom technology and equipment in all classrooms in Sugar Hall. |
Dean/Dr. Blaylock/ Technology Support |
12 month |
Funds |
Completion of project |
Bi-weekly College Administrative Council meetings |
Complete |
| d. Repair and/or replace the dysfunctional environmental control system in Sugar Hall. |
Dr. Blaylock |
12 month |
Funds |
Completion of project |
Bi-weekly College Administrative Council meetings |
This project was negated by the purchase of the Bienville building. |
| e. Replace the dysfunctional cage washer in the vivarium facility in Sugar Hall. |
Dr. Blaylock |
12 month |
Funds |
Completion of project. |
Bi-weekly College Administrative Council meetings. |
Completed February 2005. |
| *Timeline - Beginning August 2004 |